Our New Home
|
This is the new ECHO House. Construction was completed in
September 2009. The facility will accommodate 40 residents. If you would like to help us furnish the new shelter, please send your tax deductible donation to: Project ECHO |
![]() |
January - May 2009
Many pictures, lots to download!Construction Pictures
June - October 2009Dedication Pictures
October 3, 2009Trundle Bed Pictures
One of the many contributions
to make the new home a reality.
Construction Progress
| May 21, 2008 | Site Plan approved by Calvert County Planning Commission |
| December 24, 2008 | Building Permit issued by Calvert County |
| January 6, 2009 | General Contractor Notice to Proceed |
| January 14, 2009 | Construction Started!! |
| March 22, 2009 | Under Roof |
| March 25, 2009 | HVAC work started |
| March 31, 2009 | Plumbing work started |
| May 5, 2009 | Electrical work started |
| May 11, 2009 | Gas piping work started |
| June 4, 2009 | Insulation work started |
| June 12, 2009 | Drywall work started |
| June 22, 2009 | Elevator installation started |
| June 29, 2009 | Kitchen range hood work started |
| July 3, 2009 | Trim work started |
| July 5, 2009 | Parking lot curbing started |
| July 8, 2009 | Painting work started |
| July 13, 2009 | Bathroom tile work started |
| July 21, 2009 | Siding work started |
| July 21, 2009 | Flooring work started |
| July 24, 2009 | Door installation work started |
| August 4, 2009 | Plumbing fixtures installation started |
| August 5, 2009 | Bed installation started |
| August 11,2009 | Parking lot paving started |
| August 13, 2009 | Kitchen equipment installation started |
| August 25, 2009 | Landscaping work started |
| September 2009 | Cleaning and inspections |
| October 3, 2009 | Dedication |
| October 19, 2009 | Resident move in day |